Project Management Assignment 6 Answers:- Every student are requested to submit their assignments on the knowledge of their own, we do not promote copying answers. We are providing answers just as a reference.
Q1.Plant capacity refers to
(A) Number of machines in the plant
(B) Size of the plant
(C) Number of units manufactured in the given time span
(D) Number of workers in the plant
Ans:- (C) Number of units manufactured in the given time span
Q2. The investment cost per unit of capacity —— as plant capacity —— respectively.
(A) Decreases, Decreases
(B) Increases, Increases
(C) Decreases, Increases
(D) Increases, Decreases
Ans:- (C) Decreases, Increases
Q3. Which is the correct formula reflecting cost and capacity relationship?
(A) C2 = {C1 (Q2/Q1) }^α
(B) C1= {C2 (Q2/Q1 }^α
(C) C2 = {C1 (Q1/Q2 }^α
(D) C1 = {C2 (Q2/Q1) }^α
Ans:- (A) C2 = {C1 (Q2/Q1) }^α
ALSO READ : NPTEL – Online Courses,Certificate And full details
Q4. For 5000 units, the investment is Rs.1000000. What would be the investment for 10000 units. Given α = 0.6.
(A) 1515610
(B) 1515717
(C) 659754
(D) 659761
Ans:- (B) 1515717
Q5. The choice of location/site is influenced by
(A) Proximity to raw materials and markets
(B) Availability of labour and infrastructure
(C) Governmental policies
(D) All of the above
Ans:- (D) All of the above
Q6. Which of the factor should not be considered in preparing the plant layout?
(A) Proper utilization of space
(B) Smooth flow of goods from one stage to another
(C) Scope for expansion
(D) Maximization of production cost
Ans:- (C) Scope for expansion
Q7. Decision tree evaluates
(A) The risk
(B) Probability of success
(C) Potential benefits
(D) All of the above
Ans:- (D) All of the above
Q8. A decision tree is a diagram which clearly defines
(A) Potential outcomes for the collection of related choice
(B) Potential losses
(C) Potential benefits
(D) None of these
Ans:- (A) Potential outcomes for the collection of related choice
ALSO READ : NPTEL – Online Courses,Certificate And full details
Q9. In project management decision tree analysis allows the project manager
(A) To compare different course of action
(B) To compare the projects profit
(C) To find the losses
(D) To compare the risks
Ans:- (A) To compare different course of action
Q10. Project Abandonment Analysis is a process that organizations should execute before making decisions
(A) Upon halting of their projects
(B) Upon continuation of their projects
(C) Upon halting or continuation of their projects
(D) None of the above
Ans:- (C) Upon halting or continuation of their projects
Project Management Assignment 6 Answers:- Every student are requested to submit their assignments on the knowledge of their own, we do not promote copying answers. We are providing answers just as a reference.